Seawall raising in Islamorada
Seawall raising in Islamorada, where the bay tide moves 0.61 ft and the ocean tide 2.28 ft.
Free Fast Quote
Please fill out this form to request a free quote on your upcoming project and we will respond to you right away!
Cities across South Florida now set minimum seawall heights. We work out which standard applies to your lot and whether a new cap or a new wall gets you there.
- Free, no-obligation quote
- Fast response from our team
- Miami-Dade, Broward, Palm Beach and the Keys
The short answer
Islamorada's effective flood maps date from 18 February 2005, and FEMA has not yet set a date for the preliminary maps appealed in 2021. In Islamorada the Florida Bay tide swings about 0.61 ft but the Hawk Channel tide 2.28 ft, so bay and ocean lots need different designs.
Last updated
Who needs a seawall raised
Owners whose walls overtop at king tides, owners who have been cited, and owners planning a repair big enough to trigger the city's height rule.
- Water over the cap at high tide
- A city citation for overtopping
- A repair of $300 or more per linear foot in Miami Beach
- Plans to sell, rebuild or add a dock
Typical project sizes
Raising is either a new cap on a sound wall or a full new wall. Miami Beach's 2017 rule of thumb was $1,000 to $1,500 per linear foot to bring an old seawall up to code.
Bay side and ocean side tides differ fourfold
NOAA's Florida Bay gauge at Upper Matecumbe Key shows a great diurnal range of only 0.61 ft, with mean higher high water about 0.41 ft below NAVD 88, while the Hawk Channel gauge a short way across the key shows 2.28 ft (1983 to 2001 epoch). A lift or floating dock sized for one side of Islamorada is wrong for the other.
Those numbers show how much margin a raised wall really gives above an ordinary high tide.[1][2]
Flood maps from 2005, new ones pending
Islamorada still builds to effective flood maps dated 18 February 2005. Preliminary maps went through appeals between March and June 2021, FEMA has not announced when they take effect, and the Village has promised six months' notice once it does.
Raising the wall stops tidal overtopping, but the home behind it still relies on its own flood protection.[3]
Watch the datum: about 1.5 ft
The Village notes that converting from NGVD29 to NAVD88 shifts elevations by about -1.5 ft on average in Monroe County, and the shift varies from place to place. Old plans and new maps use different datums, so a cap or floor height has to be converted before anyone compares numbers.

A raise is designed to that number, measured in the right datum, and checked by survey before the cap pour.[3]
What makes Islamorada different
Principal buildings sit 20 ft from the mean high water line on altered shorelines such as canals, 30 ft on open water with conditions, and 50 ft on unaltered shorelines. Docks, lifts, davits, seawalls and riprap are water-dependent structures that may sit inside that setback under the Village's standards.[4]

Sanctuary and manatee layers
The federal small-project permit, SPGP VI, required Sanctuary sign-off before any Islamorada project in Keys waters, and crews follow the state manatee conditions on every in-water job.[5][6]

Permits in Islamorada
- Islamorada, Village of Islands, Planning and Development Services: Docks, lifts and shoreline structures under Village Code Chapter 30.
- Florida Keys National Marine Sanctuary: Sanctuary waters surround every Islamorada key from the mean high water mark; we confirm what Sanctuary approval each project needs.
- Florida DEP or South Florida Water Management District: State permit or exemption; part of the Village's water is the Lignumvitae Key Aquatic Preserve.
- US Army Corps of Engineers, Jacksonville District: Federal authorisation for work in the Sanctuary waters around the Village.
Seawall height rules by city
Each city sets its own standard, and they do not all use the same vertical datum (NAVD 88 or the older NGVD 1929), so the engineer's survey must state the wall height in the same datum as your city's rule.

Miami Beach: 5.7 ft NAVD for new walls and substantial repairs, or 4 ft NAVD designed to reach 5.7 ft. Coral Gables: a minimum of 6 ft NGVD 1929, structurally able to support 7.5 ft. Fort Lauderdale: a minimum of 5 ft NAVD88, and walls permitted before 1 January 2035 may be built at 4 ft if designed to reach 5 ft by 1 January 2050. Boca Raton: new or replaced walls between 4.0 and 6.0 ft NAVD88, designed to take another 12 to 18 inches.
City of Miami: a 2020 proposal set 6 ft NAVD 88 east of US-1. We have not confirmed it was adopted, so we check with the City for each job.[7][11][13][14][10]
Help with the cost
Miami Beach's Private Property Adaptation program accepts seawall applications on a rolling basis and reimburses 50% of costs up to $20,000, including the $2,500 assessment value; qualifying low to moderate income households need no match up to $17,500. Homes built at least 1 ft above base flood elevation are not eligible. Coral Gables waives a fee for existing homes raising seawalls for sea level rise.[8][12]

| City | Standard or incentive | Source |
|---|---|---|
| Miami Beach | 5.7 ft NAVD (or 4 ft designed for 5.7 ft) | City FAQ, June 2025 |
| Miami Beach | Grant: 50% of costs up to $20,000 | PPA program page |
| Coral Gables | Minimum 6 ft NGVD 1929, supports 7.5 ft | City Attorney opinion, 2022 |
| Coral Gables | Fee waiver for raising existing residential seawalls | City permits page |
| Fort Lauderdale | Minimum 5 ft NAVD88 | City staff report, 2022 |
| Boca Raton | 4.0 to 6.0 ft NAVD88 | Engineering Design Standards, 2025 |
Frequently asked questions
Why does it matter which side of Islamorada I live on?
Because the tide is very different: about 0.61 ft great diurnal range on Florida Bay and 2.28 ft on Hawk Channel, per NOAA gauges at Upper Matecumbe Key.
Which flood maps apply in Islamorada?
The effective maps dated 18 February 2005. Preliminary maps were appealed in 2021; FEMA will give six months' notice before they take effect.
Why do elevations on old Islamorada plans look different?
They may be in NGVD29. The Village says converting to NAVD88 shifts elevations by about -1.5 ft on average in Monroe County.
Sources
- Datums for station 8723808, Islamorada, Upper Matecumbe Key, Florida Bay (tidal epoch 1983 to 2001), NOAA Center for Operational Oceanographic Products and Services (CO-OPS), Tides and Currents. Accessed October 28, 2026.
- Datums for station 8723814, Upper Matecumbe Key, Hawk Channel (tidal epoch 1983 to 2001), NOAA Center for Operational Oceanographic Products and Services (CO-OPS), Tides and Currents. Accessed October 28, 2026.
- Floodplain Management, Islamorada, Village of Islands, Building Department. Accessed October 28, 2026.
- Ordinance No. 24-15 amending Village Code Sec. 30-1542 Shoreline Setback, with Department of Commerce Final Order COM-24-043, Islamorada, Village of Islands. Accessed October 28, 2026.
- Department of the Army State Programmatic General Permit VI (SPGP VI), SAJ-2015-2575, State of Florida, U.S. Army Corps of Engineers, Jacksonville District (document hosted by Florida DEP). Accessed October 27, 2026.
- Standard Manatee Conditions for In-Water Work (2011), Florida Fish and Wildlife Conservation Commission (FWC). Accessed October 27, 2026.
- Seawall FAQs (Miami Beach Rising Above, PDF dated 6.16.25), City of Miami Beach. Accessed October 27, 2026.
- Private Property Adaptation (PPA) program, City of Miami Beach (Miami Beach Rising Above). Accessed October 27, 2026.
- Rising Above the Risk: Frequently Asked Questions (05/05/2017), City of Miami Beach. Accessed October 27, 2026.
- City of Miami File ID 7338 (Revision A): Ordinance amending Chapters 20, 29 and 54 to set seawall minimum heights (Second Reading, printed 5/19/2020), City of Miami. Accessed October 27, 2026.
- CAO 2022-007: Legal Opinion Regarding Scrivener's Error in Zoning Code 3-706 Bulkheads and Retaining Walls (17 Aug 2022), City of Coral Gables, City Attorney. Accessed October 27, 2026.
- Solar, Open Air Dining, and Other Permits, City of Coral Gables. Accessed October 27, 2026.
- Staff Report, Planning and Zoning Board, 16 Nov 2022, Case UDP-T22010 (Tidal barrier / seawall ordinance amendment, ULDR 47-19.3), City of Fort Lauderdale. Accessed October 27, 2026.
- Engineering Design Standards Manual, section 7.7 Minimum Criteria for Waterway Features (PDF modified 10 Apr 2025), City of Boca Raton. Accessed October 28, 2026.
Get a free quote